The rescheduled BPDA-hosted community meeting for this 36-unit residential development is coming up on Tuesday evening, May 28, at 6:30 pm at the Menino Community Center, 125 Brookway Road.
We encourage attendance at this meeting. This will be a consequential development, located under half a mile from the end of the Orange Line, and as of now we at WalkUP Roslindale have the following concerns that we intend to raise on Tuesday evening:
1. Parking
- As proposed, this project is overparked. The parking ratio should be reduced from 1:1.28 to 1:1 (or less). Zero parking projects have recently been allowed in Roslindale Square, and this location is under a half mile (<10 minute walk) from Forest Hills Station (Orange Line) and steps from bus stops serviced by a dozen bus routes. Excessive parking will induce car ownership and car use, moving our neighborhood and our city away from the mode shift and greenhouse gas reduction goals to which we have committed. Reducing the amount of parking also has direct implications for the next issue.
2. Affordability
- The space saved from the above parking recommendations should be used to increase overall unit count and the number of affordable units.
- Parking should be unbundled from the residential units to increase affordability.
- We are aware that RISE’s Housing Justice group will be particularly focused on pushing the developer to increase both the percentage of affordable units and the level of affordability offered. We support RISE Housing Justice on these related issues and will make our views known at the meeting.
3. Environment
- Environmental cleanup/remediation appears to be needed on the proposed project site. While we recognize that environmental cleanup is not specifically a zoning issue, we do want to hear what the developer has to say both about what they have found and how they intend to deal with it.
- Although the project has dropped below the Large Project Review threshold and is technically required to meet only building code-based green building requirements, we would support a call for this project to exceed those standards and approach Net Zero/Zero Plus/LEED standards.
4. Surrounding Neighborhood
- The developer should assist financially with ongoing efforts around the Roslindale Gateway Path/Arboretum Road Entrance as this will be a significant amenity for residents of the development and the broader surrounding neighborhood.
- The developer should provide support for the overall improvement of Lochdale Rd, Arboretum Rd and Kitson Rd (the private way running along the site, parallel to Washington St). The developer’s application mentions a “9-foot walkway/bike path to be created as part of the project” on Kitson Rd. We would like to hear more about what is contemplated here.