Last week, we joined with several community partners to send a letter to the BPDA requesting community benefits to accompany the 18-22 Arboretum Road Development, a proposed 230-apartment development just off Washington Street abutting the Arboretum. Our joint letter focuses on funding for the Gateway Path and food pantry certification for an Archdale food distribution site. The full letter is reproduced below.
Tag: Gateway Path
Harvard-Hosted Gateway Path Community Virtual Update – November 3, 2022 at 6:30pm
As long-time WalkUP followers know, the Roslindale Gateway Path is a proposed ADA-accessible shared-use pedestrian and cycling path through the Arnold Arboretum. This project aims to extend the Southwest Corridor path system from Forest Hills bus, subway, and Commuter Rail terminus to Roslindale Village Commuter Rail Station, providing carbon-free commuting options and connecting Boston residents with the natural environment close to where they live. On November 3, 2022 from 6:30-8:00pm, the Arboretum will host a project update meeting open to members of the public (via Zoom). Register in advance for this meeting here.
Fall 2022 Gateway Path Update UPDATED with Spanish Translation
We receive frequent questions about progress on the Gateway Path, which will connect Roslindale Square to Forest Hills through the Arnold Arboretum on a nearly straight path, creating a safe green connection between JP and Roslindale and improving park access for points in between. The idea for this project helped catalyze WalkUP Roslindale’s formation early in 2015, and continues to be one of our highest priority initiatives.
To that end, please check out this detailed and recently updated presentation showing progress to date and plans for the future.
In addition, Saturday, Oct 15, 2022 is the Arboretum’s annual Crabapple and Maple festival. From 10am to 4pm, the section of South Street from Bussey St (Poplar Gate) to the Archdale Arch will be closed to traffic. The Gateway Path will be showcased at a display on South Street near the Archdale Arch. We’ll be tabling to show design plans for the the path, the boardwalk, and possible new options for pedestrian and bicycle access at the Arch entrance. We hope to see you there!
EN ESPAÑOL
Recibimos muchas preguntas sobre el progreso del Sendero de Entrada (Gateway Path), el cual conectará a Roslindale Square con Forest Hills a través del Arnold Arboretum por medio de un sendero casi derecho, creando una conexión verde segura entre JP y Roslindale y mejorando acceso al parque para los lugares entre medio. La idea para este proyecto ayudó a catalizar el empiezo de WalkUP Roslindale a principios del 2015, y continúa siendo una de nuestras iniciativas de prioridad más alta.
A ese fin, por favor vea esta presentación detallada y recién actualizada mostrando el progreso hasta la fecha y planes para el futuro.
Mas alla, sabado, Oct 15, 2022 es el Festival Anual del Arboretum de Manzanas y Arce (Arboretum’s annual Crabapple and Maple festival). Desde las 10am a 4pm, la sección de South Street desde Bussey St (Poplar Gate) hasta Archdale Arch estará cerrada al tráfico. Habrá una exhibición en South Street cerca de Archdale Arc para mostrar el Sendero de Entrada (Gateway Path). Tendremos una mesa para mostrar los planes de diseño para el sendero, paseo elevado, y nuevas posibles opciones para acceso peatonal y para bicis en la entrada de Arch. ¡Esperamos verte allí!
Translator: Grecia White.
Progress on Gateway Path funding thanks to Sen. Rush and Rep. Malia
We have been working for many years with our elected leaders to make the Roslindale Gateway Path a reality and were delighted to learn that Sen. Mike Rush has successfully pushed through an amendment to this year’s state budget bill allocating $100,000 toward development of the path. Rep. Liz Malia and her staff are on board to help see this through on the House side. This is a significant step forward for the path, which we hope will be fully funded in the coming years.
Comment letter on Boston Transportation Department Budget for Fiscal Year 2021
Last week, we sent a comment letter to the Boston City Council Committee on Ways & Means concerning next year’s operating budget, with a focus on transportation. We were particularly happy to see some proposed funding for the Roslindale Gateway Path. Other WalkUP priorities include the Washington Street Bus Lane, an American Legion Corridor bike network, and implementation of Neighborhood Slow Streets in the Mount Hope/Canterbury area. Our detail comments are below; a PDF version of the letter as sent is also available.
Spring 2020 Gateway Path Update – New 25% Conceptual Plan, Demolition Started at Bussey Brook Meadow
The Roslindale Gateway Path remains one of WalkUP Roslindale’s signature initiatives and a top priority. As we approach the five year mark since its conception (along with WalkUP itself), we’re starting to see concrete progress. Please excuse the pun.
Notably, we recently received a revised 25% conceptual plan for the path from our partner consultant, Horsley Witten Group. As you will see below, the path course has been modestly revised, and more details about eventual construction filled in. Click on the image to see an (extremely) high-resolution detailed version.
Meanwhile, demolition work on the new Bussey Brook Meadow entrance to the path–at the end of Arboretum Road off of Washington Street–recently started:
We are looking ahead to break ground for this segment of the path sometime this summer. The other major update is that design work is moving forward on the grand boardwalk connecting the Peters Hill segment of the path – this segment will connect the intersection of Bussey and South Street to the Bussey Brook Meadow. Renderings of this section are expected in June 2020. Blow-up of this section below, with the new, improved Arboretum Road entrance on the bottom right:
Community Meeting on February 28, 2019 at Menino/Archdale Community Center for Gateway Path 25% Design of Entire Path
Please join us on Thursday, February 28, 2019 at 6:30pm at the BCYF Thomas Menino (Archdale) Community Center (125 Brookway Road) to learn about the 25% design study for the Roslindale Gateway Path and provide feedback. Last summer, we had a community meeting focusing on the portion on MBTA land adjacent the Roslindale commuter rail station. This meeting will focus on the entire length of the new planned path, including the section closest to the Archdale neighborhood in Roslindale — running near the Needham Line commuter rail tracks adjacent Peter’s Hill from the entrance of the Arboretum through to the tunnel entrance at the end of Arboretum Road, and then all the way to the existing Blackwell Path. RSVP appreciated (so we can plan for the appropriate crowd) but not required.
RSVP appreciated. You can also join the event and invite others from the Facebook event page or the Nextdoor event page. Spread the word!
Community Meeting on July 25, 2018 at Roslindale Community Center for Gateway Path 25% Design of MBTA Section
Please join us on Wednesday, July 25, 2018 at 6pm at the Roslindale Community Center (6 Cummins Highway) to learn about the 25% design study for the Roslindale Gateway Path and provide feedback. This meeting will focus just on the MBTA portion of the design — the section connecting the Roslindale Square Commuter Rail Station into the Arboretum. RSVP appreciated. You can also join the event and invite others from the Facebook event page.
WalkUP Official Letter of Support for Mayor’s FY2019 Transportation Department Budget
Yesterday, we sent an official letter to Mayor Walsh in strong support of his proposed Fiscal Year 2019 transportation budget, specifically in view of several major steps forward on our most important goal for Roslindale and the City of Boston: walkability! The full text of our letter is below; we encourage everyone to drop a quick note to the Mayor and their elected representatives on the City Council to insure the active and mass transportation aspects of the budget are enacted. Once implemented, we expect residents and business owners will immediately appreciate major returns on these investments in walking, bicycle, and bus infrastructure, which will then lay the groundwork for even bigger progress in the future.
Roslindale Gateway Path 10% Conceptual Plan Public Meeting – Monday, May 8, 2017 6:30pm at Weld Hill Building in Arboretum
WalkUP Roslindale is excited to announce another milestone toward making the Roslindale Gateway Path a reality. After completing a vision report (two-page summary) with students from the Tufts Urban and Environmental Policy and Planning program just about a year ago, we raised donations to fund a “10% conceptual plan” for the path by an engineering firm, the Horsley Witten Group (“Sustainable Environmental Solutions”). This study has just wrapped up and we are holding a public event on Monday, May 8, 2017 at 6:30pm at the Weld Hill Research Building in the Arnold Arboretum, 1300 Centre Street, to present the final product and invite more community feedback and support.
Our past events for this project have had a big turnout, and we hope this one will as well. As a preview of the report, a couple of images below show in more detail the proposed route for “section 1” of the path, starting at the Roslindale Village Commuter Rail stop, as well as a visual rendering of a section of the path.
Please RSVP so we can prepare for the right size group! Spread the word, and don’t forget to join for a Jane’s Walk in the area of the path the day before (May 7).